Terminal expansion is not a typical construction project. The project team must complete civil engineering, electromechanical installation, equipment commissioning, and operational testing without disrupting existing flights, passenger flow, and ground support. Construction areas may be adjacent to the apron, baggage handling systems, or vehicle access routes, requiring any temporary power supply solution to simultaneously meet safety, flexibility, and continuity requirements.
Early in the project phase, formal power distribution facilities are often not yet in place; as equipment installation progresses, electric excavators, water pumps, construction lighting, testing tools, and maintenance vehicles generate different types of power demands. Relying entirely on long-distance temporary cables could increase wiring risks; extensive use of diesel generators requires additional management of fuel, noise, emissions, and maintenance issues.
Door Energy's Mobile EV Charger integrates energy storage, DC fast charging, and AC load power supply into a mobile device. It can be deployed between different construction areas according to the terminal expansion schedule, providing energy support for engineering equipment, temporary loads, and electric vehicles.
Its core value is not simply replacing a traditional power source, but rather helping airports establish a temporary energy system that can adapt to changes in construction phases, move with equipment locations, and continue to be used after the project ends.
![]()
I. Why are temporary power supply gaps common in terminal expansions?
Formal power distribution construction usually lags behind construction commencement
Airport expansion projects often require site preparation, foundation construction, or equipment installation to begin before the formal transformers, distribution cabinets, and fixed charging facilities are completed.
Common power-consuming tasks during this phase include:
* Excavation pit drainage and rainwater treatment
* Nighttime construction lighting
* Electric excavator and engineering equipment operation
* Temporary testing instrument operation
* Recharging maintenance and inspection vehicles
* New area GSE trial operation
If it is necessary to wait for the entire formal power grid to be completed, construction schedules and subsequent procedures may be affected.
Power Supply Locations Change Throughout the Project
Terminal expansion typically includes the following phases:
1. Site preparation and foundation construction
2. Main structure construction
3. Electromechanical system installation
4. Interior decoration and equipment commissioning
5. New area operational testing
The load, usage time, and location differ at each phase. Water pumps may be concentrated in the foundation pit area, lighting may move with the construction surface, and vehicle testing may occur at remote aircraft positions.
Therefore, temporary energy solutions must not only address "whether there is electricity," but also "whether electricity can reach the required locations in a timely manner."
II. Why are traditional temporary power supply methods inflexible?
Long-distance temporary cables increase on-site risks
Laying cables from existing power distribution points to the new terminal area may require crossing:
* Construction vehicle access areas
* Personnel access areas
* Material transportation routes
* Temporary fencing
* Ground support vehicle operation areas
Even with cable trays or protective cable racks, continuous monitoring of cable wear, waterproofing of joints, and the risk of vehicle damage is still necessary. When the construction site changes, the project team also needs to rewire and adjust the distribution boxes.
Diesel Generators Bring Additional Management Tasks
Diesel generators have strong independent power supply capabilities, but they also require simultaneous management during airport expansion:
* Fuel procurement and transportation
* On-site fuel storage and leak prevention
* Engine maintenance
* Oil and filter changes
* Exhaust emissions and noise control
* Fire and security inspections
Noise and emissions management is particularly stringent when operating near the terminal, during nighttime construction, or in semi-enclosed areas.
Fixed Facilities May Be Temporarily Idle
If fixed power distribution capacity is built based on peak construction loads, some capacity may become unusable as the project progresses into later phases.
In contrast, Door Energy Mobile EV Chargers can be repeatedly deployed across different areas, construction phases, and airport projects, improving the long-term utilization of energy assets.
Table 1: Comparison of Temporary Energy Solutions for Terminal Expansion
| Comparison Items | Temporary Cables | Diesel Generators | Door Energy Mobile Storage & Charging |
| Deployment Speed | Affected by cabling | Relatively fast | Quick dispatch |
| Location Adjustment | Requires re-laying | Movable | Can be moved with tasks |
| On-site Exhaust Gas | None | Yes | No combustion exhaust gas during discharge |
| Operating Noise | Low | High | Relatively low |
| Electric Vehicle Power Supply | Usually requires separate charging equipment | Requires external charging equipment | Can directly provide DC power supply |
| Load Response | Limited by line capacity | Suitable for continuous power generation | Suitable for variable loads |
| Routine Maintenance | Inspect lines and power distribution | Engine and fuel system | Modular electrical system |
III. How to Configure Mobile Storage & Charging Solutions Based on Construction Load?
Step 1: Establish a Complete Load List
The project team should first compile a list of all potentially connected devices, including:
* Rated Power
* Starting Power
* Daily Working Hours
* Number of Devices Running Simultaneously
* Work Area
* Task Priority
Simply adding up the rated power of all devices is insufficient. Water pumps, electric excavators, and some motorized equipment may experience higher instantaneous power consumption during startup, requiring a startup margin.
Step 2: Differentiate Between Continuous and Intermittent Loads
Continuous loads typically include:
* Drainage Pumps
* Safety Lighting
* Ventilation Equipment
* Monitoring and Communication Equipment
Intermittent loads may include:
* Power Tools
* Electric Excavators
* Maintenance Equipment
* Vehicle Quick Recharge
Continuous loads determine basic energy needs, while intermittent loads determine peak output needs.
Step 3: Calculate Daily Energy Demand
A preliminary calculation can be performed using the following basic method:
Daily Energy Consumption = Equipment Power×Usage Time×Simultaneous Use Factor
For example, if four sets of 10kW lighting equipment operate for 8 hours a day, their basic energy consumption is approximately:
4×10kW×8h = 320kWh
Actual solutions also need to consider line losses, ambient temperature, reserve capacity, and equipment efficiency; configuration cannot be based solely on theoretical results.
Table 2: Typical Load Planning Example for Terminal Expansion
| Equipment Type | Main Purpose | Load Characteristics | Planning Focus |
| Electric Excavator | Site and Foundation Construction | High Power, Intermittent Operation | Verify Starting Power and Work Cycle |
| Water Pump | Excavation Pit and Rainwater Drainage | Long-Term Continuous Operation | Reserve Continuous Power Supply Capacity |
| Construction Lighting | Night Operation | Stable Power, Long Duration | Calculated by Number of Lights and Shifts |
| Power Tools | Installation and Decoration | Intermittent Start-up of Multiple Devices | Control the Number of Devices Using Simultaneously |
| Maintenance Vehicles | Inspection and Equipment Installation | Frequent Movement | Recharge Power During Task Breaks |
| Electric GSE | New Area Operational Testing | Significant Differences in Charging Power | Verify Interfaces and Vehicle Charging Curves |
IV. How can Door Energy simultaneously support construction loads and electric vehicles?
Providing Temporary Power for AC Loads
Door Energy can provide AC power to the following loads, depending on equipment configuration:
* Electric excavators
* Water pumps
* Temporary construction lighting
* Power tools
* Inspection and maintenance equipment
This capability allows for more construction tasks compared to equipment that can only charge vehicles, reducing the number of temporary power sources on site.
Providing Fast DC Recharge for Electric Vehicles
Door Energy supports up to 420kW DC output and is compatible with CCS1 and CCS2, supporting electric construction vehicles and airport GSEs that meet interface requirements.
However, it must be clear that 420kW is the system's maximum output capacity and does not mean that every vehicle can be charged at 420kW. Actual power is determined by the following factors:
* Maximum allowable charging power of the vehicle
* Current battery state of charge
* Battery temperature
* Communication status between the vehicle and the charging equipment
* On-site power limitations
The project team should develop a recharge plan based on the specific vehicle's charging curve.
Sharing Energy Equipment Between Construction and Operations During the terminal expansion, Door Energy Mobile EV Chargers can serve construction loads during the day and recharge maintenance vehicles, inspection vehicles, and GSEs at night or during task breaks.
This sharing model improves equipment utilization and reduces the need to purchase multiple temporary power supplies and charging equipment separately.
V. How to Schedule Door Energy Mobile EV Charger Recharging and Rotation?
Recharging Equipment via DC Charging Stations Under suitable input conditions, Door Energy can recharge from 0% to 100% via DC charging stations, with an estimated time of approximately 1 hour.
The airport can schedule recharging during the following times:
* During shift changes
* Low-load windows at night
* Idle periods at fixed charging stations
* Before equipment is moved to the next construction area
Recharging via AC Power Boxes If no available DC charging stations are available on site, the equipment can also be recharged via AC power boxes, with an estimated time of approximately 2 hours.
The actual charging time will be affected by input power, ambient temperature, remaining battery power of the equipment, and system status.
Establishing Task Priorities
Under limited energy conditions, different loads should be given clear priorities:
First Priority:
* Safety Lighting
* Drainage Equipment
* Emergency Communication
* Critical Inspection Vehicles
Second Priority:
* Core Construction Equipment
* Maintenance Tools
* Operational Testing Vehicles
Third Priority:
* Non-critical Equipment that can be used later
Table 3: Illustrative Daytime Energy Dispatch Plan
| Time Period | Main Construction Tasks | Door Energy Mobile EV Charger Work Content |
| 06:00-09:00 | Drainage, Construction Preparation | Support Water Pumps and Critical Foundation Loads |
| 09:00-12:00 | Main Construction | Provide Energy for Electric Engineering Equipment |
| 12:00-14:00 | Equipment Rotation | Recharge Maintenance Vehicles and Vehicles with Low Battery |
| 14:00-18:00 | Installation and Transportation | Support Tools, Vehicles, and Temporary Loads |
| 18:00-22:00 | Nighttime Construction | Support Lighting, Drainage, and Inspection Tasks |
| After 22:00 | Low-Load Period | Recharge Mobile Energy Storage Equipment |
VI. How Does Door Energy Mobile Energy Storage Equipment Reduce Overall Project Costs?
Reducing Redundant Wiring and Temporary Power Distribution Work
Terminal expansions often involve zoned construction. If temporary cables are laid separately for each construction area, it can result in:
* Cable procurement costs
* Labor costs for installation and dismantling
* Costs of protective equipment
* Distribution box relocation costs
* Post-completion restoration costs
Door Energy mobile energy storage equipment can be moved with the construction area, reducing redundant investment.
Reducing Downtime and Waiting Losses
Temporary power outages can cause:
* Construction personnel waiting
* Equipment idle
* Wasted nighttime windows
* Delays in related processes
* Schedule extensions
For airport projects, construction time windows are typically very limited. The value of quickly restoring power may outweigh the simple difference in energy costs.
Enhancing Asset Value After Project Completion
After the terminal expansion, Door Energy can continue to be used for:
* Peak-hour power replenishment for ground support vehicles
* Emergency apron rescue
* Runway maintenance power supply
* Other airport construction projects
* Government emergency support tasks
Therefore, project evaluation should consider the cross-scenario use value of the equipment, rather than just calculating the cost of a single project.
VII. How to Build an Energy System that Coordinates Fixed Power Grid and Mobile Storage & Charging?
Fixed Power Grid Handles Long-Term Stable Loads
Formal power distribution systems are better suited for:
* Terminal lighting
* Air conditioning and ventilation
* Baggage handling systems
* Fixed charging areas
* Long-term operational facilities
These loads are located in fixed locations and have long usage cycles, and should be supported by a stable fixed power grid.
Door Energy Mobile EV Charger Handles Variable and Emergency Loads
Door Energy Mobile EV Chargers are ideally suited for:
* Transitional power supply before grid connection
* Construction loads with constantly changing locations
* Rapid power replenishment for electric engineering vehicles
* Peak-hour capacity replenishment
* Emergency power supply during temporary outages
* Equipment testing in new areas
Modular Maintenance Improves Project Continuity
Door Energy's modular design allows for module-level troubleshooting and replacement when a local module malfunctions, which helps to:
Shorten fault diagnosis time
* Reduce prolonged downtime of the entire unit
* Simplify spare parts management
* Reduce long-term maintenance costs
For airport projects with tight deadlines and limited construction windows, maintainability is a crucial factor in ensuring project continuity.
Conclusion
Temporary power supply during terminal expansion involves more than just configuring a generator or laying a cable; it requires a comprehensive approach tailored to the project's phases. A comprehensive energy dispatch plan should be established based on phases, load changes, construction locations, and flight operation requirements.
The Door Energy Mobile EV Charger, with its energy storage, up to 420kW DC charging, CCS1/CCS2 interface compatibility, AC load power supply, OCPP communication, and modular design, provides flexible energy support for construction equipment, temporary lighting, water pumps, maintenance vehicles, and electric GSEs.
It can fill power gaps before the formal power distribution system is completed, and can also undertake commissioning, emergency backup, and peak capacity replenishment tasks in the later stages of the project.
For airport operators, engineering contractors, and government airport management departments, the significance of mobile energy storage and charging goes beyond solving one-time construction power needs; it provides an energy asset that can be repeatedly deployed across multiple projects and operational scenarios.
FAQ
Q1: At which stage of terminal expansion is Door Energy best deployed?
A1: It can be used for transitional power supply before the completion of the formal power distribution facilities, and is also suitable for phases such as main construction, electromechanical installation, nighttime construction, commissioning of new area equipment, and operational testing.
Q2: What construction equipment can Door Energy support?
A2: Depending on the system configuration, it can power AC loads such as electric excavators, water pumps, construction lighting, power tools, and maintenance equipment. It can also provide DC charging for electric vehicles that support CCS1 or CCS2 interfaces.
Q3: How long does Door Energy itself take to fully charge?
A3: Under compatible input conditions, it takes approximately 1 hour to fully charge from 0 to 100% via a DC charging station and approximately 2 hours via an AC charging box. Actual time will be affected by input power, ambient temperature, and equipment status.
Q4: Is the maximum 420kW output suitable for all vehicles?
A4: Not suitable for all vehicles. Actual charging power depends on the vehicle's allowable power, battery state of charge, temperature, communication protocol, and site settings.
Q5: Can mobile charging completely replace fixed power distribution systems?
A5: It is not recommended as a complete replacement for long-term fixed power grids. A more reasonable approach is to have the fixed power grid bear the long-term basic load, while mobile energy storage and charging stations are responsible for transitional power supply, variable loads, peak energy replenishment, and emergency backup.